Safety
Safety is an urgent concern when associated with
anything nuclear. The decommissioning process
is certainly a moment in a nuclear reactors lifetime
that requires a high level of safety and attention.
This following information is related to the United
Kingdom Atomic Energy Authority (UKAEA) and its
decommissioning safety procedures. There are also
other systems and methods explained to make the
safety aspect of decommissioning effective and
financially viable. This paper outlines some of
the experience gained by the combined UKAEA and
Contractor project team in obtaining safety approvals
for the work.
Who takes care of Safety?
The decommissioning process requires timely clearance
of protocol and documentation to be successful.
All dismantling operations have to be subjected
to stringent scrutiny of the safety arrangements
and this is undertaken through the submission
and approval of safety-cases and modification
proposals.
Different strategies have to be adopted by the
team to seek task safety approvals whilst maintaining
the scheduling of the work program, and at the
same time ensuring that safety standards are maintained.
Contractors and governing bodies like the UKAEA
(United Kingdom Atomic Energy Agency) team are
contracted to decommission reactor sites. The
project management of the decommissioning, the
dismantling itself, the development of the tooling
and methodologies and the preparation of the associated
safety submissions are all the onus of these said
bodies.
Project Management of the Decommissioning
Different protocols are established within these
bodies to ensure the safety of their employees
and the public. Inventories of Nuclear Liabilities
and the establishment of Nuclear Safety Accounts
and Safety Assessment and Feasibility Interim
Reports help make the decommissioning process
manageable and financially viable.
Committees categorise different safety systems.
An example of the UKAEA safety system is as follows:
The objective of this process is to determine
the level of scrutiny that should be applied to
the submission, and is not any comment about how
realistic the hazard is perceived to be. Subsequently
there would be other protocols adopted by other
governing bodies to ensure safety and a means
to categorise the level of safety.
The Inventory of Nuclear Liabilities involves:
- Drawing up a register specifying the location
and condition of all nuclear facilities and
all sites containing radioactive substances
on Belgian territory;
- Estimate of the cost of decommissioning and
cleaning up these facilities and sites;
- Evaluation of the availability of sufficient
funds to carry out these future or ongoing operations;
- Updating the inventory every five years.
Nuclear Safety Account
To assist in the decommissioning process there
are a number of methods employed to ensure decommissioning
financially viable. The uses of Nuclear Safety
Accounts in Europe have been a decision that has
answered the concerns for finance.
As an example a result of the Munich Summit, a
multilateral fund was established with the agreement
of the European Bank for Reconstruction and Development
to perform the management function for a Nuclear
Safety Account. The mandate of the Nuclear Safety
Account is to use donor contributions for the
execution of priority, short-term projects to
complement bilateral programs.
Figures quoted and established for projects total
EUR 262 million have been awarded.
Further examples of the Nuclear Power Plant projects
have been contracted at Kozloduy in Bulgaria,
at Ignalina in Lithuania, and at the Kola, Novovoronezh
and St. Petersburg nuclear plants in Russia.
The last project awarded is in Ukraine, which
provides short term safety improvements for the
remaining operating unit at Chernobyl and decommissioning
facilities in preparation for closure.
Safety Assessment and Feasibility Interim Reports
The disposal of decommissioned nuclear reactor
waste is a very real burden. The use of these
safety and feasibility reports make a way for
the viability of removal and safe storage of nuclear
waste. These assessment and feasibility reports
are preliminary reports on the safety and feasibility
of deep underground disposal. An example would
be the SAFIR 1 report which assessed the work
carried out between 1974 and 1988 on the possible
disposal of radioactive waste in the Boom clay
layer in Belgium. The SAFIR 2 report assesses
the work carried out in the years 1990-2000.
The Dismantling Itself
During
the Decommissioning process the health and safety
of employees, contractors and the general public
is paramount. Goals are that no harm should result
from activities.
Working towards this, goals strive to:
- Eliminate injuries at work
- Prevent incidents but maintain effective emergency
arrangements
- Achieve and sustain an excellent safety culture
- Learn the lessons from events, implement corrective
actions and seek out and use good practices
wherever we may find them
- Ensure that activities, products and services
are in compliance with applicable legislation
and meet the requirements of good practice and
applicable standards of employment health and
safety performance.
In short, safety is of the utmost importance.
It is an integral part of everything that is done.

An example of the methodology in action is the
following report outlining guidelines followed
by a joint U.S. and Kazakhstan agencies effort.
This decommission was for a sodium cooled reactor
in Kazakhstan.
Technical Strategy For The Project
The strategy for development of the plan involves
a series of tasks, the basic accomplishment of
which is in a series of joint workshops, training
sessions, and/or working meetings of all participants
occurring either in the U.S. or Kazakhstan ---
dependent on cost effectiveness and travel restrictions.
In these workshops the technical experience of
decommissioning sodium cooled reactors will be
transferred to Kazakhstan engineers and scientists
with the particular knowledge of the BN-350 reactor
systems. In parallel with the workshops, detailed
technical design concepts will be developed for
near-term key activities such as sodium draining
and processing. All this information will be combined
in a technical decommissioning plan. The tasks
are as follows:
Tasks 0 and 1 - Develop Initial Workshop
Plans and Conduct Workshop to Develop the Format,
Content, and Initial Data Requirements for the
Plan
The key goals of this task are to develop the
detailed format and content of the Shutdown Plan
for International Review (henceforth called 'the
plan'), to develop preliminary data needs to write
the plan, and to prepare the detailed plans for
the writing of the plan. The format and content
document should be in sufficient detail so that
an appropriately assigned individual could develop
the information for an assigned section of the
plan to permit acceptable drafting of that section.
Task 2 - Develop the Information Base
and Strategy for the Plan Development
The intent of this task to collect all the data
that is needed to compete the plan. The available
data identified in task 1 is collected and evaluated,
and additional data needs are identified as necessary
based on this assessment. A strategy for fulfilling
the data needs is agreed upon. It is envisaged
that this step will be performed in a second 1
to 2 week workshop. The predominant data need
is expected to involve a) confirming the list
of actions and tasks needed to place the plant
in SAFESTOR, and b) gathering support
information to document the logic, schedule, and
resource requirements for those actions and tasks.
Quantities of radioactive waste, doses, etc.,
and other task specific information may also be
convenient to estimate with analysis of each of
these actions so that it may be systematically
tallied in the plan. Clear direction is given
in the workshop on how the data is to be collected.
Assignments are given at the end of the workshop
for the collection of the data in conformance
with the strategy and the workshop concluded.
Personnel return to their home bases to collect
the information as necessary. Information already
collected at the workshop from available information
is archived by appropriate section in the format
and content documents that it supports. Detailed
technical concepts developed in task 6 will begin
to be fed into the planning process at this time.
Task 3 - Develop the Plan
This task includes 2 aspects:
- Assembling all the data and information gathered
in task 2, reviewing it, and creating a rough
draft of the plan. This will be performed in
a final (third) 1 - 2 week workshop. The most
difficult part of this task is probably assembling
the resource-loaded schedule.
- Complete the final writing of the plan. A
'writing team' is agreed upon to take the rough
draft and turn it into a final document ready
for review.
The technical concepts being developed in task
6 will continue to be updated as more information
is obtained.
Task 4 - Review, Revise, and Approve the
Plan
This task takes the conformed draft plan and
assures it is acceptable to the workshop participants,
U.S. and Kazakhstan decision makers, and it is
appropriately approved for international review.
Task 5 - Conduct International Peer Review
of the Plan
In parallel with the performance of this contract,
the joint Kazakhstan-U.S. decision-makers communicate
with the IAEA to set up an international peer
review of the BN-350 shutdown plan. Conceptually,
the IAEA will administer the peer review by identifying
and recruiting international experts to review
the plan. These experts cannot be the ones who
may have been involved in the creation of the
plan. Revision B of the draft conformed plan is
sent to these reviewers approximately 1 month
prior to a review meeting.
The review meeting is conceptually sponsored by
the IAEA and conducted in Vienna.
Task 6 - Concept development of Near-Term
Tasks Necessary for Detailed Planning
This task develops the detailed design concepts
for near-term tasks where there is a substantial
amount of development work required in order to
figure out what to do specifically sodium draining
and processing. Unless this is done, the planning
work that will be performed will be based on conjecture
on areas that will take place in the near term
potentially invalidating the plans for the follow-on
work. The team required for the general planning
work is comprised of engineers and scientists
with a broad plant knowledge. Developing the detailed
concepts requires the addition of specialists
to develop the specific design concepts.
Specific detailed concepts need to be worked
out for the following:
- Sodium draining
- review for trapped residual sodium areas
- develop strategy for draining trapped sodium
- determine need for aux heating
- development of sodium draining process)
- Sodium Processing
- Determine location of processing facility
and connection to plant
- development of sodium processing concept
- review of environmental acceptability of processing
product
- development of licensing requirements for
the facility)
Task 7 - Contract Adminisatration
This task involves work by the Kazakhstan Nuclear
Technology Safety Center to manage the designated
work with the other agencies within Kazakhstan
and Russia in support of this project. KNTSC responsibilities
include general coordination of all project activities,
administrative review of deliverables (to assure
completeness prior to payment), translation of
the deliverables as necessary, arrangement for
and implementation of payment and material procurements/transfers
to appropriate personnel at the
other agencies, confirmation of payment/material
receipt, administrative and logistic support for
project workshops, and maintenance of financial
records, wages paid, and other payment documentation.
Development of the Tooling and Methodologies
The goal of decommissioning:
- The decontaminating of facilities (activities
intended to reduce, or even eliminate, all traces
of contamination);
- The dismantling of facilities (all dismantling,
cutting and demolition operations with a view
to withdrawing contaminated and/or activated
materials and structures from service);
- The management of the radioactive waste resulting
from the operations above
All these operations, which are performed with
due consideration of the safety of the operators
taking part and of the facilities and sites
concerned, are intended to bring the residual
radioactivity to a level permitting the release
of the facility for unrestricted use.
Other procedural methods to ensure safety include
categorisation of risk. An example of categories
established by the UKAEA include:
There are 4 categories:
- Category D refers to a building incident with
trivial affect on the operator,
- Category C being a more serious event affecting
only the operator whilst
- Category B has effects outside building
- Category A has effects outside the site boundary.
Release defined:
Release is defined as the removal of all further
regulatory radiological control by the competent
authorities (Federal Agency for Nuclear Control)
of substances, materials, facilities or sites
for the reason that the associated risk has become
sufficiently low. Implicit in the concept of release
is the understanding that once said substances,
materials, facilities or sites have been released,
they are no longer subject to any restriction
or radiological control. Consequently, radioactive
materials that has been released, can be treated
as residues or ordinary effluents, and substances,
materials, facilities or sites that have been
released for re-use or recycling can be sold or
transferred to any person, company or association
that is then free to use them for any purpose.
A way in which the decommissioning process has
been made "cleaner" is the use of recycling
of nuclear decommissioning waste.
In Belgium the ONDRAF/NIRAS bodies have adopted
the following methods:
The decommissioning of Belgian nuclear facilities
will be the main source of the radioactive waste
that bodies like ONDRAF/NIRAS manage. Belgian
has therefore opted resolutely for a strategy
of minimising the volume of radioactive waste
produced during decommissioning operations, through
extensive decontamination and the recycling of
decontaminated materials. As a result, ONDRAF/NIRAS
predicts that around only 3% of all the materials
present on a nuclear site will need to be managed
as radioactive waste.
For more information about the state of affairs
at European Union level see: The European Commission
Website on Decommissioning of Nuclear Installations
Services in Safety and Reliability in regards
to tooling and methodology include the following:
- Safety Criteria Development (design phase,
operating facilities, plant decommissioning).
- Fault/Hazard Identification in support of
safety, reliability and risk assessments, including
HAZOP studies, FMEA techniques etc.
- Safety Assessments including supporting analysis
of hazards, vulnerability and damage.
- Availability, Reliability & Maintainability
of existing and novel Process Plant.
- Maintenance Optimisation including Reliability
Centred Maintenance.
- Design Optimisation/Justification, from a
safety viewpoint.
- ALARA/ALARP Studies, both qualitative and
quantitative.
- Safety Case Preparation, to meet HMNII and
other licensing requirements.
- Independent Peer Review of safety, reliability
and risk assessments and safety cases, on behalf
of both the licensee and the licensing authority.
- Consequence Modeling, to address effects to
both on-site and off-site groups.

References:
- http://www.nirond.be/engels/7.7_Ontmanteling_eng.html
- http://www.ukaea.org.uk/wagr/docs/IBC_RCA.pdf#search=
'decommissioning%20%20safety'
- http://www.bnfl.co.uk/index.aspx?page=123
- http://www.ntsc.kz/projects/istc513.htm
|