Cost
The cost of decommissioning a nuclear power plant
varies according to a number of factors. Site-specific
factors such as the type of reactor, labour costs
and waste management, as well as the sequence
and timing of decommissioning stages are all variable.
(1)
Decommissioning cost estimates are necessary
however to guide government policy, to assure
funds will be available when needed and to serve
as a basis for industrial strategy and planning.
(2)
The Nuclear Energy Agency OECD's 2003 report
(2) produces decommissioning
estimates for a variety of nuclear power reactors
from 26 countries around the world. The cost identified
for decommissioning a nuclear power plant encompasses:
- faculty shut-down activities
- procurement of material
- dismantling activities
- security and surveillance
- waste treatment and disposal
- site cleanup
- project management and engineering
- research and development
The range in cost for nuclear decommissioning
is as follows:
| Table 1: The costs of decommissioning
by reactor type |
| Reactor type |
Cost to decommission in US dollars (using
exchange rate of 1st July 2001) |
| Western Pressurised Water Reactor (PWR) |
$200-$500/KWe* |
| VVER (Russian light water pressurised reactor) |
$200-$500/KWe |
| Boiling Water Reactor (BWR) |
$300-550/KWe |
| CANDU/ Heavy Water Moderated Reactors |
$270-430/KWe |
| Magnox /gas cooled reactors |
Up to $2600/KWe |
*KWe= Kilowatt-electric, one thousand watts of electricity
capacity.
Note that all costs are undiscounted and fuel management
costs are not included in the decommissioning costs
here.
The data for the cost estimates ranges shown
in figure 1 is based on past experience, scaling
from the decommissioning of other nuclear facilities,
as well as non-nuclear decommissioning and activity-based
models of the specific site being decommissioned.
Most cost estimates are based on a specific engineering
cost model, the NEA/IAEA/EC cost model. (2)
From the data sets collected from the OECD survey,
dismantling contributed between 25-34% of the
total cost while waste management ranged from
17-43%. Security, engineering and site cleanup
each averaged around 10% of the total decommissioning
costs while the remaining cost items did not exceed
5% in any case. The data suggested that for PWR,
BWR and VVER reactors, immediate dismantling as
opposed to deferral had no immediate impact on
the overnight decommissioning cost; however the
decommissioning strategy did affect the amount
of the discounted cost.
Funding
As decommissioning expenses will be incurred
long after the plant is established, decommissioning
costs represent a future financial liability.
In nearly all countries the operator is responsible
for the decommissioning funds. If the plant is
state owned, as is the case for Lithuania and
Hungary, the costs are distributed between the
utility and the state. Regulatory requirements
vary from country to country. In approximately
50% of the 26 countries surveyed by the OECD,
the accumulated funds are required to cover all
decommissioning expenses at the time of plant
shut down.
In the United States for example, the Nuclear
Regulatory Commission requires that licensees
establish a decommissioning fund for each reactor
and every year licensees must review the amount
of money required for decommissioning and the
adequacy of collections. Estimates are adjusted
periodically to account for change of labour costs,
energy, technological advancements and low-level
waste disposal.
Due to the nature of the funds, they build up
slowly and then accelerate as compounded earnings
on the trust funds investments increase. Assuming
the plant has a 40-year life span, in the 30th
year, half of the funds are expected to be collected.
The Nuclear Energy Institute (3)
estimates the total cost of decommissioning the
United State's 104 reactors to cost $40 billion,
of which $22.5 billion is already collected from
ratepayers. The average cost of decommissioning
a nuclear power reactor in the United States is
US$370 million. (1998 Figure) (4)
In 60% of the countries included in the OECD report,
funds are collected by a charge included in the
consumer's electricity price.
In the United States 0.1-0.2c per KWh is collected
to fund decommissioning. Other options utilised
to collect funds include compulsory fees, Government
funding and contributions from donor organisations.
What happens if a nuclear plant is required
to be shut down before planned?
If the plant is required to be shut down prior
to the completion of its estimated life (~40years)
decommissioning funds are still needed, but almost
certainly won't be available. The cost of decommissioning
in this case is often shared between the consumers
and the stakeholders. In 1997, the American reactor
'Main Yankee' was shut down 11 years prior to
expiration and costs were distributed between
ratepayers and shareholders. An introduction of
a non-bypassable wires charge may be introduced
to account for the advent of early decommissioning.
Another option is government funding, but this
must compete with other government priorities
such as healthcare and education.
References
- http://www.eu-decom.be/about/decominshort/whatis.html
-
"Decommissioning Nuclear Power plants:
Policies, Strategies and Costs" 2003,
Nuclear Energy Agency, Organisation for Economic
Co-operation and Development,
- Nuclear
Energy Institute Website
- "Decommissioning
Nuclear Facilities: Nuclear Issues Briefing
Paper 13" 2005, Uranium Information
Centre, Australia
-
Nuclear Regulatory Commission Website
|