UOW
Excellence - Innovation - Diversity
University of Wollongong
Nuclear Power & Australia
Nuclear Power & Australia
Site Search
Advanced Search  

Skip Navigation

NukeWeb
   
Research Topics
   
Fuel & Waste
   
Reactors
   
Decommissioning
   
 
 
 

Case Study - Fire Damaged Reactors

In this section we will be looking at a case where a nuclear reactor core was damaged by fire. We will be taking a brief look at the cause of the fire and then investigating the various difficulties encountered, as well as methods and options being implemented during the decommissioning process in this difficult case. This has been divided into the following categories:

Background

  • 1946 - Britain still had considerable worldwide defense responsibilities & commitments, thus they needed an independent deterrent.
  • 1947 - Work began on 2 reactors at Windscale Cumbria UK (Pile 1 and Pile 2). The purpose of these was for the production of weapons-grade plutonium.
  • 1950 - Pile 1 went critical in October.
  • 1951 - Pile 2 went critical in June.
  • 1952 - The first plutonium produced by midyear.
  • Figure 1 shows the pile from above at this time.

Problem

  • Wigner growth in the graphite moderator was known of at the time (and design taking that into account), however the phenomenon of Wigner energy was not known.
  • What is Wigner energy? It is an increase in potential energy due to the displacement of atoms in the lattice when bombarded by neutrons.
  • How to avoid this problem: The stored energy in the graphite moderator can be released by annealing.
  • What if annealing not carried out? A spontaneous and potentially dangerous release of heat can occur. 1952 - Such a release of energy was first seen in Pile 2 in May when an unexpected temperature rise was seen in the core. Soon after a similar event occurred in Pile 1 while the reactor was shut down.
  • The Wigner energy phenomenon was finally recognized and deliberate annealing was periodically conducted on each reactor from this time till October 1957.
  • 1957 - The period between anneals was extended from 30,000 to 40,000 MWdays.

Disaster

  • 1957 - October 7, an anneal had begun on Pile 1 but a fire started in the heart of the core which was not extinguished until October 11, four days later.
  • The fire showed that there were very serious flaws in the design of air-cooled reactors, both from a technical and safety point of view.
  • Both Piles have been shut down since the accident and no reactors of this design have ever been built again.

POCO

  • 1958-1961 - The Post Operational Clean Out (POCO).
  • The POCO included:
    • Insertion of control & shutoff rods, none of which pass through the fire-affected zone (FAZ)
    • Dismantling & removal of operating gear
    • Sealing of the outlet air ducts connecting the core space to the chimney
    • Provision of ventilation plant to provide containment via depression
    • Removal of the fuel cartridges from the air outlet and outlet ducts; Isolation of the water duct from the cooling pond; Clean out, draining and sealing of the water duct

     

The In Between Years

  • 1961-1990 - There was not too much that could be done on the core due to the current technology of the time.
  • Since the current critical state of the core was unknown periodic core surveys were carried out.
  • These were to determine if any neutron poisons needed to be injected into the core prior to dismantling operations.
  • There is also the problem of possible voids within the FAZ, which could cause a collapse during dismantling.

Phase 1 - Remote Control

  • Another pass-time during the "in-between years" included planning, design and construction.
  • Planning - Obviously involves figuring out - "How the hell are we gonna pull apart this wreak?" - and without killing anyone?
  • As one would expect, the high background radiation levels vastly restricted significant human access to the worksite.
  • Design & Construction - The solution to this problem was to build a dedicated remote operated vehicle (ROV), in fact they made a few of them!
  • Introducing:
    • Below Left - The Norman submersible ROV.
    • Below Right - The Cyclops ROV (used for inlet air duct fuel and debris collection).
  • Both these ROVs were instrumental in phase 1 of decommissioning Pile 1. The ROV's were used in various ways. For example:
    • Repairing and creating watertight seals in the ducts
    • Removing radioactive sludge and lose contaminated particles
    • Removing obstacles for other ROV's
    • And also for freeing ROV's that got stuck!
  • Basically the ROV's did all that was not accessible by humans in some way or another.
  • A further in-depth report on how they were used can be found at this website:
    • http://www.ukaea.org.uk/windscale/nearticle.htm

     

 

  • Phase 2 - Core Dismantling

  • UKAEA carried out optioneering studies to examine a number of commercial proposals to decide how to carry out the work of dismantling the core.
  • Some of these options included carrying out the work:
    • In air;
    • Under water;
    • In an Argon atmosphere.
  • An Argon inerting solution was eventually decided upon as it was determined the there should be no chance of fire in the core during dismantling.
  • At the time the article used was written preparation work was being carried out to allow core dismantling.
  • This can be split into 3 categories:
    • Material and structures peripheral to the core;
    • Undamaged graphite blocks and fuel from the core;
    • Fire damaged zone potentially fused and disordered.
  • It has been decided that they intend to dismantle the core from both the inlet air and water duct.
  • A transfer tunnel is being constructed to allow waste to be moved from the water duct to the inlet air duct.
  • The use of manipulators deployed on vertical masts in the inlet air and water ducts to dismantle the core was closely examined.
  • This was finally rejected on operability and ALARA grounds.
  • Thus as with phase 1, all processes will have to be carried out by ROV with CCTV feedback.
  • Core dismantling will proceed from top to bottom using the ROV's equipping a variety of tools and placing the waste in skips for transfer to the WPF.

Predicted Waste

  • All materials within the core are assumed to be waste.
  • Predicted waste includes:
    • Graphite 2 x 106 kg;
    • Stainless steel 11 x 103 kg
    • Isotope cartridges 2 x 103 kg;
    • Aluminium 7 x 103 kg
    • Uranium 15 x 103 kg;
    • Cadmium 0.6 x 103 kg
    • Mild steel 140 x 103 kg
    • Cast iron 4 x 104 kg
    • The exception to this of course is the undamaged fuel cartridges, as these are reprocessible.

     

Currently And Beyond

  • At this point in time phase 2 of the Pile 1 decommissioning process is underway.
  • Final decommissioning and dismantling is expected to be completed sometime during the year 2015.
  • Below is an artist's depiction of Pile 1 now (Top) compared to the year 2050 (Bottom).

References

 
 
 

University of Wollongong
Wollongong NSW 2522 Australia
UOW Switchboard: +61 2 4221 3555

Prospective Student Enquiries
Australia: 1300 367 869
International: +61 2 4221 3218

CRICOS Provider No: 00102E
Privacy, Disclaimer and Copyright
Feedback: webmasters@uow.edu.au